Siemens F01911 fault code meaning

Siemens / F01911

Series: DCM-6RA80

PB/PN: Isochronous synchronization cycle fault

DC drive

Meaning: During cyclic operation, errors in the global control telegram used for cycle synchronization, or violations of the time unit specified by the configuration telegram (see bus cycle Tdp and Tpllw), have persisted for several DP cycles.

Possible causes

Source: SINAMICS DCM, Parameter Manual, firmware version 1.5 SP2 (based on 5.1 SP2) P982

Series: G120-CU250S-2

PB/PN Isochronous synchronization cycle fault

converter

Meaning: During cyclic operation, errors occurred in the global control telegram used to synchronize the cycle, or the time unit specified in the configuration telegram was exceeded (see bus cycle Tdp and Tpllw). These errors persisted for several DP cycles.

Possible causes

Source: SINAMICS G120, Control Unit CU250S-2 P1338

Series: G130-G150

PROFIBUS: Clock synchronous operation, clock cycle

converter

Meaning:

Possible causes

Source: G150 P841

Series: G200, G210X, G220

PN: Cycle fault during isochronous synchronous run

converter

Meaning: The telegram for cycle synchronization failed during several consecutive bus cycles or arrived outside the specified time window during several consecutive bus cycles (see bus cycle Tdp and Tpllw).

Possible causes

Source: SINAMICS G200 converter P683; SINAMICS G210X converter P937; SINAMICS G220 converter P1282

Series: S110

PB/PN Isochronous synchronization cycle fault

servo drive

Meaning: During cyclic operation, the global control telegram used to synchronize the cycles is faulty, or the time unit specified by the configuration telegram has been exceeded (see bus cycle Tdp and Tpllw). These errors have persisted for several DP cycles.

Possible causes

Source: SINAMICS S110 P988

Series: S200, S210

PN: Cycle fault during isochronous synchronous run

servo drive

Meaning: The telegram for cycle synchronization failed during several consecutive bus cycles or arrived outside the specified time window during several consecutive bus cycles (see bus cycle Tdp and Tpllw).

Possible causes

Source: SINAMICS S200 PROFINET_SIMOTICS S-1FL2 P499; SINAMICS S210_SIMOTICS S-1FK2 and S-1FT2 P1310

Series: S220

PN: Cycle fault during isochronous synchronous run

converter

Meaning:

Possible causes

Source: SINAMICS S220 Converter P2190